梨树建设在石油化学领域以丰富的经验为本在持续发展。

现以各产业领域专业性和高度的技术力为本,在TURN-KEY BASE 및 DESIGN-BUILD崭露头角,以无误差的精密施工在PLANT事业的所有领域硕果累累。

National Agency for Administrative City Automatic Collection Facility 3-1 Project 
位置
National Agency for Administrative City. Sejong  
项目规模
Automatic Collection Facility pipe construction (length : 23.3km, construction area : 4,849,800 m2) 
项目期
2014-06-26 ~ 2017-07-31 
National Agency for Administrative City Automatic Collection Facility 3-1 Project
KPIC ONE Project Work Package 4 construction 
位置
In Korea Petrochemical Ind., Onsan-eup, Ulju-gun 
项目规模
NCC facility related tank 9 units, jetty and truck loading installation 
项目期
2015-11-30 ~ 2017-05-31 
KPIC ONE Project Work Package 4 construction
KPIC ONE Project Package 4 
位置
Korea Petrochemical Ind. Onsan 
项目规模
NCC equipment Tank 9 unit, Jetty / Truck Loading installation 
项目期
2015-11-30 ~ 2017-05-31 
KPIC ONE Project Package 4
Samcheok Eco-Building material Plant PJ 
位置
Korea Southern Power Co. Samcheok 
项目规模
Building material or Cement admixture 400,000 ton/year production plant 
项目期
2015-03-17 ~ 2017-03-15 
Samcheok Eco-Building material Plant PJ
3-1 facility construction of automatic clean net in administrative complex city 
位置
In administrative complex city, Yeongi-myeon, Sejong Special Self-governing City 
项目规模
Automatic clean net tuning construction 19.9 km construction area 4,849,800 m2 
项目期
2014-06-26 ~ 2017-02-25 
3-1 facility construction of automatic clean net in administrative complex city
JSTT NO.3 Berth TANK Terminal Construction (1 stage) 
位置
JeongilStolthavenUlsan. Onsan 
项目规模
Pipe Rack 1 unit, Connection Bridge 2 unit, Manifold 2 unit, Lighting, Paving  
项目期
2016-09-01 ~ 2017-01-31 
JSTT NO.3 Berth TANK Terminal Construction (1 stage)
Samcheok Eco construction material mass production plant construction 
位置
In Korean Southern Power, Wondeok-eup, Samcheok-si 
项目规模
Construction framework and cement mixture 400,000 ton/year production 
项目期
2015-03-17 ~ 2016-07-16 
Samcheok Eco construction material mass production plant construction
Underground tubing construction for hydrogen supply to Deokyang Onsan/Isu Chemical 
位置
Whole area of Isu Chemical, Onsan 
项目规模
Underground plumbing construction of 12” x 8km for hydrogen supply (2 indentation) 
项目期
2015-01 ~ 2016-03 
Underground tubing construction for hydrogen supply to Deokyang Onsan/Isu Chemical
JSTT-DOW SADARA PROJECT 
位置
In Onsan and Ulsan new port 
项目规模
1 appurtenant facility and 7 storage tank installation 
项目期
2014-11 ~ 2015-10 
JSTT-DOW SADARA PROJECT
Cheotmaeul complex life waste automatic collection facility construction 
位置
Cheotmaeul Village, Sejong 
项目规模
Life waste treatment 
项目期
2009-11 ~ 2015-06 
Cheotmaeul complex life waste automatic collection facility construction
KPIC EOG Project 
位置
Korea Petrochemical Ind. Onsan 
项目规模
EO (80,000 MTA)/EG (205,000 MTA) production facility and related appurtenant installation 
项目期
2013-06 ~ 2015-01 
KPIC EOG Project
Addition of D-Sol reactor and installation of activation system facility 
位置
Isu Chemical Onsan 
项目规模
Addition of 1 D-SOL reactor and activation system installation 
项目期
2013-04 ~ 2013-12 
Addition of D-Sol reactor and installation of activation system facility
Petasys waste water/atmosphric processing facility installation 
位置
In Isu Exaboard, Ansan 
项目规模
Waste water/atmospheric facility installation 
项目期
2013-02 ~ 2013-05 
Petasys waste water/atmosphric processing facility installation
NPT Project 
位置
Korea Petrochemical Ind. Onsan 
项目规模
Ball tank unit 4 and appurtenant construction 
项目期
2011-08 ~ 2012-09 
NPT Project
GOC(TC) LAB Project 
位置
Taicang, China 
项目规模
LAB production facility construction 
项目期
2010-09 ~ 2012-05 
GOC(TC) LAB Project
OTK E4 Project 
位置
Odjfell Terminal Korea, Onsan 
项目规模
Tank 15 items installation 
项目期
2010-09 ~ 2011-10 
OTK E4 Project
New Waste Heat Boiler of Stoker #1 & #2 installation 
位置
KG Eco Service Korea, Siheung 
项目规模
Steam production boiler 2 unit replacement and performance improvement 
项目期
2010-07 ~ 2011-05 
New Waste Heat Boiler of Stoker #1 & #2 installation
RSCL Project 
位置
S-Oil Onsan 
项目规模
Civil engineering, mechanic, framework, plumbing, electricity and instrumentation, etc. 
项目期
2009-11 ~ 2010-10 
RSCL Project
IPA Project 
位置
Isu Chemical Onsan 
项目规模
Electronic IPA dryer installation and upgrade of IPA 30,000 ton/year 
项目期
2007-04 ~ 2008-03 
IPA Project
IPA Project 
位置
Isu Chemical Onsan 
项目规模
Civil engineering, mechanic, framework, plumbing, electricity and instrumentation 
项目期
2007-04 ~ 2008-03 
IPA Project
CTA Reactor Area machine/tubing installation 
位置
Taegwang Industrial, Onsan 
项目规模
Civil engineering, framework, mechanic, plumbing, painting, instruemtnation, thermal insulation, etc. 
项目期
2006-10 ~ 2007-10 
CTA Reactor Area machine/tubing installation
S-OiL SHU PROJECT 
位置
S-Oil Onsan 
项目规模
Design, civil engineering, mechanic, plumbing, electricity and instrumentation 
项目期
2006-02 ~ 2007-04 
S-OiL SHU PROJECT
S-Oil Naphtha Storage Tank production and installation 
位置
S-Oil Onsan 
项目规模
Naphtha Storage Floating Root Tank 25,000 m3) production, installation and peripheral plumbing construction 
项目期
2006-07 ~ 2007-03 
S-Oil Naphtha Storage Tank production and installation
Slitter line equipment relocation 
位置
Pungsan, Pyeongtaek  
项目规模
Civil engineering, mechanic and plumbing 
项目期
2006-11 ~ 2007-02 
Slitter line equipment relocation
Ochang Science Complex waste water treatment facility installation 
位置
Ochang, Chungbuk development office 
项目规模
Physical, chemical and biological treatment 
项目期
1998-05 ~ 2006-12 
Ochang Science Complex waste water treatment facility installation
EP repair 
位置
Incheon, Ansan, Sihwa cogeneration plants 
项目规模
EP SYSTEM 
项目期
2006-03 ~ 2006-12 
EP repair
Daewoo Shipbuilding & Marine Engineering comprehensive waste water processing facility construction 
位置
Daewoo Shipbuilding & Marine Engineering, Geoje 
项目规模
Biological treatment (SBR technique) 
项目期
2000-02 ~ 2002-12 
Daewoo Shipbuilding & Marine Engineering comprehensive waste water processing facility construction
Mokdong and Nowon cogeneration plants denitrification facility 
位置
Seoul Energy, Seoul 
项目规模
Denitrification facility, electricity, civil engineering and instrumentation 
项目期
2001-07 ~ 2002-01 
Mokdong and Nowon cogeneration plants denitrification facility
2nd factory expansion water processing facility construction 
位置
Isu Petasys, Daegu 
项目规模
Waste water, water purification and pure water treatment facility 
项目期
2000-04 ~ 2000-09 
2nd factory expansion water processing facility construction
NP 5TH REVAMPING P/J 
位置
Isu Chemical Onsan 
项目规模
NP storage tank installation and revamp construction 
项目期
1999-09 ~ 2000-06 
NP 5TH REVAMPING P/J
Doksan-dong comprehensive waste water processing facility construction 
位置
Geumcheon-gu office, Seoul 
项目规模
Renovation 
项目期
1999-08 ~ 1999-11 
Doksan-dong comprehensive waste water processing facility construction